The Various Forms of Percent Complete
At the beginning of 2019, Financial Accounting Standards Board (FASB) and the International Accounting Standards Board (IASB) jointly implemented the Accounting Standards Codification (ASC) 606, Revenue from Contracts with Customers. Essentially, ASC 606 now requires forms to recognize revenue from contracts with customers when goods or services are transferred. For professional services firms that use their expertise to sell their time, this has a significant impact on how firms recognize revenue.
About FASB ASC 606
With the new guidelines in ASC 606, firms must recognize revenue in their income statement during the period in which the revenue is earned and not when it is billed. Since professional services firms manage projects that can span across multiple periods, they might not bill until the project is complete. As a result, firms must use a form of percent complete for the project to determine how much revenue to state on their income statement for that period. For example, if during a specific period a firm completes 25% of the project, they must recognize 25% of the revenue that will be earned from the contract for that period.
There are three distinct ways to calculate percent complete:
- Billing Percent Complete
- Financial Percent Complete
- Physical Percent Complete
Billing Percent Complete
Using billing percent complete is the most common method. Typically, this is driven by the project manager during the invoicing process. There are two options:
- Overall percent applied to the total contract value
- Percent complete by phase used to invoice based on the various components of scope/deliverables and these phases are broken down using either internal or external contract value
For many firms, this also drives revenue or earnings. Furthermore, it is recommended for people to review the current FASB 606 regulations. This will explain why earning what you invoiced may not be an acceptable solution any longer.
Financial Percent Complete
Another common technique is the financial percent complete. The formula for this method is job to date/job to date + estimate to complete. This indicates how much of the total estimate at completion has been spent or burned. When applied to the contract value, we can calculate revenue. Deltek Vision can facilitate this calculation using Resource Planning.
Physical Percent Complete
Lastly, physical percent complete can be utilized. This is usually calculated when the user or project manager has entered and can provide the following:
- Compared to financial percent complete, indicated whether the project’s progress is tracking with the financial burn
- When begin to drive earned value
- Have control earnings based upon contractual stipulations such as deliverables which can accelerate or slow down earnings and at the same time drive Work in Process (WIP) in tandem but that is separate from invoicing
Which Form is Right for Your Firm?
Let’s do some homework. Using a project your firm is executing, calculate/stipulate all three forms of percent complete and compare them. Then write a business case elaborating on the project’s health from these three statistics. You might surprise yourself with the results.

Mergers and acquisitions (M&A) in the architectural and engineering (A&E) industry are on the rise. Unfortunately, many firms are not prepared to successfully implement the M&A process. With an acquisition, it is imperative that the “buying” entity have a well-defined set of procedures to easily onboard the incoming firm. In the case of a merger, all involved firms would need a set plan which would dictate the transition to a new firm. However, first a firm must decide the direction it will take regarding the M&A process and evaluate how it will affect the current organization’s structure.
With the New Year approaching, it is a fitting time for accountants and project managers to review the previous year and identify areas of improvement. While we usually think of New Year’s resolutions for our personal lives, there can also be professional ones. Let’s take a look at some of them.
The following account is a true story. It begins with an AE firm recognizing the need for change in order to support its growth. This firm quickly realized that bringing disparate systems to one integrated platform like Deltek Vision was the fix they needed.
There has been an uptick in interest recently from C-Level financial leaders to become more involved with the CRM functions within Vision. You may ask yourself why this new trend is occurring since the CRM module of Vision is for marketing and business development functions. The reason must surely be based on an informational need so that actionable decisions can be made.
A KPI, or Key Performance Indicator, is a measurable value that demonstrates how effectively a company is achieving crucial business objectives. Organizations should use KPIs to evaluate their success at reaching targeted goals. Simply stated, KPIs provide your firm with metrics that compare budgeted amounts to the actual values. KPIs are no longer just for accounting and finance as they now reach deeper into a firm’s operational side examining marketing, business development and project management.
Within Deltek Vision lies a very handy tool, which enables a firm to have multi-company functionality. However, the benefits of this multi-company functionality feature seem to elude many firms that would greatly appreciate its capabilities. So let’s talk in detail about multi-company functionality and the why, when and how firms should use this fantastic feature.
For project-based firms, timesheets are essential to ensure that an employee’s time is reflected to a specific project. I’m sure you already knew this, but do you manage timesheets correctly in Deltek Vision? Here are some facts and best practices for different scenarios to help you better manage timesheets in Deltek Vision.
Most firms that I work with utilize independent contractors to supplement their workforce. This isn’t a blog about “walks and talks like an employee, must be an employee.” For that, I recommend a good labor attorney. However, what I am going to clue you in on is about the proper way to track and account for independent contractor’s time in Deltek Vision.
You know you have spent your whole workweek devoted to a specific project, but you’re only showing 35 hours being billed/charged to the project. Where did the value of those 5 hours go? In many cases, these missing hours can be attributed to non-billable labor, and many AEC firms overlook the importance of documenting how this time is spent. However, accurately accounting for non-billable labor is extremely important to track accurate project performance.